BPM305: Project Scheduling and Control Assignment, SUSS, Singapore Use the information contained below to compress one-time units per move using the least-cost method
University | Singapore University of Social Science (SUSS) |
Subject | BPM305: Project Scheduling and Control |
Question 1
Use the information contained below to compress one-time units per move using the least-cost method. Demonstrate how you can reduce the schedule until you reach the crash point of the network.
For each move, identify which activities were crashed, and the adjusted total cost, and explain your choice if you have to choose between activities that cost the same. Indirect costs for each duration are indicated in Table 1.2 below:
- Which activities were crashed and the adjusted total cost?
- Explain your choice if you have to choose between activities that cost the same.
- Compute the optimum cost-time schedule for the project and the associated cost.
Hire a Professional Essay & Assignment Writer for completing your Academic Assessments
Question 2
There are two tunneling machines (T1 and T2) that will bore from the same starting place to the endpoint. Their lengths are 2160m and 2348m respectively. T1 shall start 40 days before T2. They both shall proceed at the same rate of 8m/day. The tunnels need precast segment rings to be installed as they bore. The ring production schedule is 4 rings/day on a 6-day/week basis. The precast segment ring is to be installed as the tunneling machine bores the tunnel.
Assuming that T1 starts on 1 Jan 2023, calculate:
- Completion dates for each of the machines.
- How many precast segment rings are required per tunnel (at 1.5m/ring)?
- Production time of the precast segment rings.
- Installation time of the precast segment rings (A minimal lag of 100m is to be
maintained between the tunneling machine and the installation of the rings) - When is the latest date to start the production of the precast segment rings in order to meet the tunneling needs? Assume that the precast segment rings can be installed immediately after casting.
- The production of the precast segment rings is delayed due to some unforeseen circumstances. To catch up with the production, 2 additional molds are made available on top of the 2 existing molds. Analyze the impact on the completion date with this move.
At Myassignmenthelp.sg, we understand the importance of high-quality essay writing in achieving academic success. Our team of experienced and professional writers is dedicated to providing students with the best essay writing assistance. With our assignment help Singapore, you can be confident that you will receive a high-quality essay that will help you achieve your academic goals.
- MTH316 Assignment 02: Heat Shield and Semiconductor Manufacturing Analysis Jan2025, Singapore
- QTS0109:Comprehensive Statistical Analysis and Insights on Customer Satisfaction and Resurant Performanceta, CA1 Singapore
- Addressing Behavioral Challenges in the Classroom: Analysis and Intervention Strategies| Assignment, Singapore
- Understanding Autism: Diagnosis, Challenges, and the Importance of Early Intervention| ASD Assignment, Singapore
- Religious Switching and Pluralism in Southeast Asia| Essay, Singapore
- MGT555:Comprehensive Company Environmental Analysis Report| GBA-January 2025 Semester,Singapore
- MGT555: Innovative Strategies and Future Growth in the Gaming Industry| ECA-January Semester 2025
- PAR301:Strategies for Countering Radicalization: Lessons from Canada’s History| Essay, Singapore
- ICT285:Database Implementation and Views for FineFoods4U Case Study
- A2359C-Pharmaceutical Sales and Marketing Project Assignment: AY2024 Term 4 Guidelines
UP TO 15 % DISCOUNT