BPM209 Cost Management for C&S Works Assignment, SUSS, Singapore: Prepare a take-off list with the corresponding CEMS clauses and unit of measurement for measuring
Question 1
With reference to Figure Q1.1,
(a) Prepare a take-off list with the corresponding CEMS clauses and unit of measurement for measuring the excavation and reinforced concrete work.
(b) Apply measurement techniques to take off quantities for the excavation and reinforced concrete works.
Specifications:
(i) All excavation work shall commence from the existing ground level.
(ii) Lean concrete shall be of grade 15 and 75 mm thick.
(iii) The raft foundation slab shall be 400 mm thick.
(iv) All reinforced concrete shall be of grade 30.
(v) Formwork shall be of sawn timber.
(vi) Reinforcement for raft foundation slab shall consist of two layers of Fabric Mesh type A393 weighing 6.16 kg/m 2
(vii) Concrete cover is 50 mm thick
Hire a Professional Essay & Assignment Writer for completing your Academic Assessments
Question 2
(a) Compare the difference between a trial pile and a working pile and the different types of static load tests applied to them.
(b) With reference to Figure Q2.1, prepare a take-off list with the corresponding CEMS clauses and units of measurement for measuring reinforced concrete bored piles including reinforcement.
(c) With reference to Figure Q2.1, apply the measurement technique to take off quantities for the reinforced concrete bored piles.
(d) With reference to Figure Q2.1, apply the measurement technique to take off quantities for the reinforcement work.
Specification for Piling:
(i) All reinforced concrete bored piles shall be 1100 mm in diameter, of grade 35 concrete, and reinforced with 22 H28 mm diameter main bars and H12 mm diameter circular links @ 250 mm centers.
(ii) The estimated bored depth of piles is taken from the existing ground level.
(iii) All piling operations shall commence from the existing ground level.
(iv) Maintained working load test shall be executed on two piles up to 1.5 times the designed working load of 220 tonnes.
(v) Concrete cover shall be 75 mm thick.
(vi) Assume 50 working piles to be installed.
(vii) Rock is encountered at the last 500 mm depth of boring.
Buy Custom Answer of This Assessment & Raise Your Grades
Question 3
With reference to Figure Q3.1, identify the scope and interpret the drawing.
(a) Identify the relevant CEMS rules relating to sub-heading and classification
requirements and explain how they are applied to the measurement of the steel roof trusses which do not form a major part of the structure.
(b) Apply measurement technique to take-off quantities for the steel roof truss.
Stuck with a lot of homework assignments and feeling stressed ? Take professional academic assistance & Get 100% Plagiarism free papers
Calling all Singapore University of Social Science (SUSS) Students! Struggling with your BPM209 Cost Management for C&S Works Assignment? Look no further! We offer top-quality TMA (tutor-marked assignments) and individual assignment assistance in Singapore. Our expert Homework Helpers are here to support your academic journey. Trust us for the best assignment help in Singapore, and we'll guide you through tasks like preparing a take-off list with CEMS clauses and units of measurement for measuring. Don't let assignments hold you back; pay our experts and excel in your courses.
- Final Assignment: Migrating FashionOnline’s Infrastructure to AWS: A Strategy for Enhanced Availability and Data Protection
- HRM331: Talent Management – Strategic Shift from the War for Talent to the Wealth of Talent
- Marginalised Populations – The Structural and Cultural Exclusion of People Experiencing Homelessness in Singapore
- CVEN3501 Assignment 2: Groundwater Modelling of Drawdown from a Pumping Bore
- CSCI312 Assignment 2: Conceptual Modelling and Implementation of a Data Warehouse and Hive Queries
- CH2123 Assignment: Fugacity, VLE Modeling & Applications of Henry’s Law
- BAFI1045 Assignment -Constructing and Evaluating Passive and Active Portfolios Based on the Straits Times Index (STI)
- FIN2210E/FIN2212E Group Assignment: Financial Risk Management Analysis of Bursa Malaysia Companies
- FLM101 Assignment: A Film Analysis: Stylistic Techniques and Their Thematic Importance
- HRM Assignment Answer: Talent Transformation in the Age of AI: Turning Challenges into Opportunities via Ecosystem Innovation
UP TO 15 % DISCOUNT