BPM305: Project Scheduling and Control Assignment, SUSS, Singapore The duration and direct cost for each activity in the network of a small construction contract under both normal and crash conditions
The duration and direct cost for each activity in the network of a small construction contract under both normal and crash conditions are given in Table Q1.
Determine the following:
(a) Cost slope for each activity.
(b) Normal cost of the project.
(c) Cost associated with crashing each activity till a stable critical path is obtained.
(d) Provide reasoning for choosing the activity at each stage of (c) above.
(e) Least cost and crash duration.
(f) What conclusion can you draw from the results?
For your computation, use Indirect (overhead) costs of $125 per day.
Question 2
Apply scheduling and control techniques to improve project processes.
The progress of a tunneling project that involves five contracts has been given in Table Q2. Each project uses a few Tunnel Boring Machines (TBM) that drill the ground to make a tunnel. The table shows the Contract name, TBM name, Length that the TBM has to bore, and the progress achieved by each in five calendar months.
Analyze the data and compute the following:
(a) Which machine has made the maximum progress?
(b) Which Contract has made the maximum progress?
(c) Which month has the highest progress – by machine and Contract.
(d) What are the overall progress in percentage (%) and meters?
(e) Which project is expected to finish the last?
Buy Custom Answer of This Assessment & Raise Your Grades
Achieve Academic Success with our Expert Assistance at Singapore University of Social Sciences (SUSS)! Struggling with summative assessments, group-based assignments, or need Online Exam Help? Look no further! Our online assignment help service is here to assist you. We specialize in BPM305: Project Scheduling and Control at SUSS, Singapore. Our experts can help you analyze the duration and direct cost for each activity in the network of a small construction contract under both normal and crash conditions. Don't let the complexities of your coursework overwhelm you – pay our experts and excel in your studies at SUSS!
- Imagine that you are currently working for a precision medicine startup: Machine Learning Paper Review in Precision Medicine, Written Assignment 1, NUS, Singapore
- Go Business offers PSG solutions for enterprises in Singapore: Collective Intelligence and Entrepreneurship, Assignment 1, JCU, Singapore
- Design an ontology based on- Accidents can be categorised as chemical, electrical, fire, kinetic or liquid: Collective Intelligence and Entrepreneurship, Assignment 1, JCU, Singapore
- Project Control Monitoring, Assignment, HU, Singapore: Deliberate Project MONITORING AND CONTROL or PMC Identification
- DSM500: Final Project Report, Coursework 2, UOL, Singapore
- DSM080: Financial Markets, Assignment, UOL, Singapore: A grapefruit juice futures contract is for 15,000 pounds of frozen grapefruit juice
- DSM080: Financial Markets, Assignment, UOL, Singapore: The share price of a certain stock today is $42.50, and five-month European style call options with a strike price of $45 currently sell for $4.25.
- DSM080: Financial Markets, Assignment, UOL, Singapore: A trader who is working in the gold markets is able to borrow money at the interest rate of 7% per annum
- DSM080 Financial Markets, Assignment, UOL, Singapore: A dollar-based American corporation has decided that it will have to pay 6 million UK pounds in three months
- Principle of Finance Assignment, UCD, Singapore: National Gaming Inc. (National) operates the weekly lottery in the country
UP TO 15 % DISCOUNT