BPM307 Tutor-Marked Assignment 01
Question 1
Your new residential development project has commenced the design stage and your client has requested for the preliminary cost plan to be based on the condominium project completed in 2019. Below is the cost plan for the said completed project with a total GFA of 50,000m 2 awarded in 3Q 2016.
Cost Plan for ABC Condominium
| s/n | Descriptions | Elemental cost |
|---|---|---|
| 1 | Substructure Works | $6,000,000 |
| 2 | Civil & Structural Works | $30,000,000 |
| 3 | Walls | $5,000,000 |
| 4 | Wall Finishes | $3,000,000 |
| 5 | Floor Finishes | $9,000,000 |
| 6 | Ceiling Finishes | $1,500,000 |
| 7 | Doors and Windows | $5,000,000 |
| 8 | Roof and Finishes | $15,000,000 |
| 9 | Carpentary & Joinery | $8,000,000 |
| 10 | Metalworks | $5,000,000 |
| 11 | Sanitary & Fittings | $6,000,000 |
| 12 | Signages & Sundries | $1,000,000 |
| 13 | Mechanical Works | $12,500,000 |
| 14 | Electrical Works | $5,550,000 |
| 15 | External Works | $7,500,000 |
| Sub-Total | $120,050,000 | |
| 16 | Preliminaries | $12,005,000 |
| Total Construction Cost | $132,055,000 |
Table 1
Proposed Project Brief:
The total GFA for the project is 75,000m2 with an additional 25,000m 2 basement carpark. References
- Appendix 1 – Cost references of Singapore Construction Cost Data.
- Appendix 2 – BCA Tender Price Index
(a) State FIVE (5) assumptions in your cost estimate for the total construction cost.
(b) Prepare the elemental cost plan for the proposed development showing the elemental rates and the elemental cost for the proposed development.
(c) Derive the project unit rates for the estimated construction cost:
(i) Cost per GFA
(ii) Cost per CFA
Question 2
(a) Explain the factors contributing to the substantial increase in the construction cost unit rate as compared to the past project based on the elemental cost plan, Table 1.
(b) Advise the client on the value engineering option(s) to optimize the carpark provision for the project. In your advice, you are to explain the options and indicate the potential cost savings and assumptions based on your recommendation(s)
Get Your BPM307 TMA 2026 Done Right—On Time, Every Time
Many SUSS students find this BPM307 cost planning and estimation assignment difficult, especially when it comes to preparing elemental cost plans, applying cost indices, and calculating accurate unit rates for new projects. It can be confusing to link past project data with current estimates. If you’re also facing such issues, you can get expert cost planning assignment help from My Assignment Help SG, tailored to your SUSS requirements. You can also explore singapore university of social science assignment examples to understand the correct approach, and then choose service write my assignment to get a customised, plagiarism-free solution prepared just for you.
- Social and New Media Written Report (40%): Website Message and Method Analysis with Strategic Recommendations | Murdoch
- ENG235 AIoT End-of-Course Assessment July 2026: PowerGrid SG Smart Grid and Utilities Case | SUSS
- BME363 ChatEHR End-of-Course Assessment July 2026: Large Language Models in Clinical Care | SUSS
- IBM380 International Business Capstone Management Project: Research Paper and Slide Presentation Brief (BBA)
- BUS329 Single Index Model Group Assignment TS 2026: Beta, Alpha and Risk Decomposition | Murdoch University
- Social and New Media Website Revamp Proposal: Digital Strategy Design Document | Murdoch
- Mentoring: Theory and Practice Essay: Collaboration in Mentoring Relationships | Kaplan
- NUR5731 Foundations of Integrated Care Thematic Literature Review 2026 | NUS
- LOG309 Industry 4.0 Logistics Applications ECA July 2026 | SUSS
- BUS304 Accounting Theory and Accountability Group Case Study TJA 2026 | Murdoch University