BPM305 Tutor-Marked Assignment Two: Project Scheduling, Cost Optimization, and Control
| University | Singapore University of Social Science (SUSS) |
| Subject | Project Scheduling and Control |
TUTOR-MARKED ASSIGNMENT TWO (TMA02)
This assignment is worth 14% of the final mark for BPM305 Project Scheduling and Control.
The cut-off date for this assignment is 26 March 2025, 2355 hrs.
Note to Students:
You are to include the following particulars in your submission: Course Code, Title of the TMA, SUSS PI No., Your Name, and Submission Date.
Question 1
Determine the normal, least cost, and crash durations for the following project. Calculate the cost associated with each duration and optimum cost/time for the given project network below.
cta_quesition_1
Time units are in weeks
If the indirect costs for each duration are $1,200 for baseline duration and $1,130 for 15 weeks, $1,000 for 14 weeks, $900 for 13 weeks, $860 for 12 weeks, $820 for 11 weeks, and $790 for 10 weeks, tabulate the Total Costs by duration.
For each cycle, identify which activities were crashed, the adjusted total cost, and explain your choice if you must choose between activities that cost the same.
Compute for 6-7 cycles till you cannot crash anymore. For each cycle, indicate clearly
(a) Which activities were crashed and the adjusted total cost. (22 marks)
(b) Explain your choice if you must choose between activities that cost the same. (21 marks)
(c) Tabulate the project duration alongside the direct cost, indirect cost, and total cost and illustrate these values on a cost-time graph. Compute the optimal cost-time schedule for the project and the associated cost. (17 marks)
Question 2
Demonstrate understanding of Project Control.
Peach manufactures high tech devices for public. Currently, the executive team is developing a new version of their smartphone. As with all their products, they intend to design the smartphone to meet current trends and manufacture the device in-house to maintain quality standards. Estimates have been made for the development process to bring the project to the
manufacturing stage. The company aims to meet the product specifications, prioritize adherence to the project timeline, and is prepared to incur additional costs to achieve a tighter schedule.
Use the information provided in Table Q2 and demonstrate your competency in using Microsoft project Software by:

(b) Find the completion date by including only recognised Singapore holidays.
(15 marks)
(c) Find the project cash flow and represent it as a monthly bar chart and S-Curve (15 marks)
cta_quesition_2
- MTH359 Applied Financial Mathematics I Tutor-Marked Assignment 01, 2026
- RES511 Research Methods in Science and Engineering Tutor-Marked Assignment 01, 2026
- 6KNIS605 Fundamental Knowledge and Skills in Older Persons Care Assessment Brief 2026
- ICT348 Information Security Offence Defence and Incident Management Tutor-Marked Assignment 01, 2026
- MTH212 Statistical Analysis Tutor-Marked Assignment 2026 | SUSS
- EAS109 Thermo-Fluid Mechanics Tutor-Marked Assignment 01, 2026
- BUS105 Statistics Group-based Assignment 2026 | SUSS
- BPM505 Collaborative Contracting in Built Environment Tutor-Marked Assignment 01, 2026
- EAS435 Manufacturing Systems Tutor-Marked Assignment 1, 2026
- TLL304 Applied Linguistics Tutor-Marked Assignment 01, 2026