DCE003: ESTIMATION AND COSTING Assignment, Singapore You are the quantity surveyor of your company and recently your company is taking part in the tender to build a single story house
The purpose of this assignment is to:
L01: Understand the types of estimation used in the construction industry.
L02: Understand analysis of rates used in the construction industry.
L03: Understanding various excavation types.
L04: Understand different methods of taking out estimates.
L05: Understanding different methods of valuations.
Questions
1. You are the quantity surveyor of your company and recently your company is taking part in the tender to build a single story house. Based on the following tender drawing and table you calculate the following using center line method:
S. No | Description of work | Unit | No | Measurements | Volume | ||
L | B | H | |||||
1 | Excavation for foundation | M3 | |||||
2 | Concrete in foundation | M3 | |||||
3 | Brick work in cement mortar
1st step 2nd step 3rd step 4th step 5th step |
M3 | |||||
5 | Interior-Plastering works ( deduct at doors and windows) | M3 | |||||
6 | Brick works volume from ground floor level to ceiling level | M3 |
a. Earth work for foundation volume
b. Lime concrete volume in foundation
c. Brick work with cement mortar volume
d. Interior-Plastering works ( deduct at doors and windows)
e. Brick works volume from ground floor level to ceiling level (25 marks)
2. Calculate the number of cement bags, sand & aggregate for M 20 (1:1.5:3) & M15 (1:2:4) concrete having a volume of 19 m3 & 35 m3 respectively.
Calculate the sand & cement requirements for 2 m3 of CM 1:6 & CM 1:4
Estimate the quantity of earthwork for a portion from the following data:
Road length | 0m | 30m | 60m | 90m | 120m | 150m |
FORMATION RL | 210 | 209 | 208 | 207 | 206 | 205 |
EXISTING RL | 206.80 | 205.20 | 203.00 | 204.50 | 202.00 | 201.50 |
3. Prepare a lead statement for the following items: –
S. No | Material | Rate at source | Lead in KM | Conveyance charges $ per KM | Cess charges $ | ||
MT | CT | ST | |||||
1 | Cement | $2500/ 1 TONS | 5 | 5 | 3 | 6 | 25 |
2 | Bricks | $95/1000 Nos | 2 | 5 | 6 | 7 | 20 |
3 | Sand | $25/m3 | 7 | 8 | 9 | 10 | 35 |
4 | 40mm HBG metal | $300/m3 | 8 | 6 | 7 | 9 | 15 |
The formation level starts at RL 210.000 and the chainage length assumes 30m. The proposed road shall be at the falling gradient of 1 in 30. The side slope shall be 2:1 and the width of the road shall be 10m. Use the Mid-section rule, Trapezoidal rule & Prismoidal rule.
4. Estimate the quantity of earthwork for a portion from the following data:
Road length | 0m | 30m | 60m | 90m | 120m | 150m |
FORMATION RL | 210 | 209 | 208 | 207 | 206 | 205 |
EXISTING RL | 206.80 | 205.20 | 203.00 | 204.50 | 202.00 | 201.50 |
5. Prepare an estimate for a proposed commercial complex for a private owner and following are the given data:-
a. Plinth area-1500 m2/floor
b. Height of each floor- 4m
c. No of storeys-G+5
d. Cubical content rate- S$32/m3
Provided the below are the percentage of the structured cost
a. Water supply & Sanitary- 4.5% for each of them
b. Electrical-7%
c. Fluctuation rates- 5%
d. Contractor profit-12%
e. Petty supervision- 4%
6. What are the various methods of valuation and briefly explain
7. Briefly explain various types of excavation works with pictures
Buy Custom Answer of This Assessment & Raise Your Grades
Looking for assignment help in Singapore for your DCE003: ESTIMATION AND COSTING assignment at Singapore University of Social Sciences (SUSS)? Look no further! Our expert team is here to assist you. As the quantity surveyor of your company, we understand the importance of accurate estimation and costing in tendering for projects like building a single-story house. Our experienced professionals can provide you with top-notch assistance in completing your TMA, individual assignments, and even offer an exceptional essay writing service. Don't let the stress of your coursework overwhelm you; trust our reliable service to help you excel in your studies. Pay our experts and gain the confidence you need to succeed!
- CVE2322 Recyclable Gantry Design Assignment Project: Sustainable Civil Engineering Model Challenge
- BMG706 Strategic Quality Change Assignment Report: Enhancing Operational & Quality Management at any Organization
- CVE2323 Structural Systems Report: Analytical & Computational Study of Portal and Frame Structures
- BMK3015 Major Project Assignment Report: Real-World Marketing Solutions for Industry Client Using Research Insights
- BCLO001 Business Statistics Assignment: Exercise Duration Analysis Among Temasek Polytechnic Students
- BM4364 Customer Experience Management Report: Evaluating CX Practices Through Employee Interview in the Service Industry
- GSFM7514 Financial Decision-Making Assignment: Analysis of Costing, Budgeting, and Investment Strategies for SAC, MEMC, and CCID
- BM0973 Crisis Management Assignment: BCRM Analysis of the 2022 Genting Highlands Landslide Disaster
- AC0779 Strategic Management Assignment Essay: Culture’s Role in Shaping Healthcare Strategy and Organisational Outcomes
- ComfortDelGro Organisational Structure Assignment: Analysis for UNGC-Aligned Sustainable Transport Strategy
UP TO 15 % DISCOUNT